The boiler is in, it is firing and the customer is making you a tea. This is the moment the paperwork gets skipped. A rushed handover is what causes trouble later: a customer who says you never told them anything, a buyer's solicitor asking for proof the boiler was fitted properly, or a warranty claim that goes nowhere. This guide covers what to check, record and leave behind on a new boiler job.
What the law makes you check before you leave
The main rule is regulation 26 of the Gas Safety (Installation and Use) Regulations 1998. It applies in England, Wales and Scotland. Under regulation 26(9), after work on a gas appliance you must immediately examine:
the effectiveness of any flue
the supply of combustion air
the operating pressure or heat input, or both where necessary (if neither is reasonably practicable to examine, check combustion performance instead)
the operation of the appliance, to make sure it works safely
Regulation 26 does not name a particular form you must hand over. But these checks are exactly what a commissioning record should show you did, so write the results down at the time rather than from memory later.
Other points in regulation 26 to show the customer
Regulation 26(5): you must not leave the appliance connected to the gas supply unless it can be used safely, or the supply is sealed off with an appropriate fitting.
Regulation 26(6): the appliance must have a means of shutting off the gas at its inlet, unless that is not reasonably practicable. Show the customer where it is.
Regulation 26(2): a flued domestic appliance must be connected to the gas supply by a permanently fixed rigid pipe.
The paperwork to hand over
Put everything in one folder or one email so the customer can find it in five years' time. A sensible set is:
The completed commissioning record. This is the checklist that comes with the boiler or that your competent person scheme asks for, such as the Benchmark checklist, filled in with the results of the checks above. Sign and date it. The Building Regulations require the system to be commissioned, and the notice of commissioning goes to building control, so the signed checklist is the customer's own proof that it was done.
The manufacturer's instructions and user manual. Leave the ones that came in the box. Do not take them away for your own files. The customer needs them, and so does the next engineer.
Your compliance certificate or notification. If you fit the boiler as a member of a competent person scheme, the Building Regulations 2010 (regulation 20) require you to give the occupier a copy of the certificate that the work complies, and to notify building control, within 30 days of finishing. In practice your scheme usually sends both for you. Tell the customer to keep it, because buyers' solicitors often ask for it.
Warranty details. Leave the warranty paperwork, the registration reference if you registered it, and any conditions such as an annual service.
Your own details. Include your name, business name, Gas Safe registration number and how to reach you if something goes wrong. Say what the guarantee on your labour covers.
A copy of the invoice. It shows the date, the make and model, and what was done. It is useful evidence if anyone queries the job.
Talk the customer through it
Paper alone does not make a good handover. Take five minutes to show the customer:
where the gas shut-off is and how to use it
how to work the controls, set the timer and check the pressure
what to do if they smell gas or the boiler stops working
where the paperwork is and that they should keep it
Note on the commissioning record or your job notes that you did this. It is a small line that can matter later.
If you find a defect you can't fix on the day
Regulation 26(9) also says you must "forthwith take all reasonable practicable steps to notify any defect" to the responsible person and, where different, the owner of the premises. For an LPG (liquefied petroleum gas) appliance where neither is reasonably practicable, you notify the gas supplier. In any other case, you notify the transporter.
The regulation does not say the notice must be in writing, but a short written note, with a date and a copy kept for yourself, is far easier to defend than a conversation on the doorstep. If you turn the supply off or seal it, say why and record it.
Keep your own copy
Before you leave, photograph the signed commissioning record, the certificate or notification, the data plate and the finished install. Store them with the job and the invoice. If a customer questions the work or a sale falls through, you can show what you checked and when. Regulation 26 does not set a retention period, so it is worth asking your competent person scheme or checking GOV.UK for how long to keep records.
If you use Quidjob, you can keep the job notes, photos and invoice together on your phone and send the invoice from site while the handover is fresh.
Wrap-up
Do the regulation 26(9) checks, write down the results, and leave the customer with the commissioning record, manuals, certificate, warranty details and invoice. Show them the gas shut-off and keep your own copy. Rules on certificates can differ by nation and by scheme, so check the official pages or ask your scheme provider if your situation is unusual. This is general information, not legal advice. If you also work on rented homes, see our guide to landlord gas safety and EICR rules.