A customer asks what you would knock off if they paid straight away. Or you are short on cash and wonder about offering 5% off for quick payment. Either way, a discount is money you give away for certain, in return for getting paid sooner. Whether that is a good swap depends on how much sooner and what your cash is worth to you. This post gives you a quick calculation to run before you quote. It is general information, not tax or legal advice.
What an early-payment discount really costs
Say you quote £2,000 for a bathroom refit, with payment due 30 days after the invoice. You offer 2% off if the customer pays within 7 days. A customer who takes the offer pays £1,960. You lose £40 and get your money 23 days earlier.
£40 sounds small. To see if it is, turn it into a yearly cost so you can compare it with other ways of finding cash. This is simple arithmetic, not an official figure, and it is only a rough guide.
Divide the discount by what you would receive after it. For 2% off, that is 2 ÷ 98.
Work out how many days earlier you get paid. Normal due date of 30 days, minus 7 days, is 23 days.
Multiply the first answer by 365, then divide by the days from step 2.
So 2 ÷ 98 × 365 ÷ 23 is about 32% a year. That is what you are effectively paying for getting your money 23 days sooner.
Now try a bigger offer: 5% off if paid within 14 days, on the same 30-day terms. You get paid 16 days earlier. 5 ÷ 95 × 365 ÷ 16 comes to roughly 120% a year. Unless you are truly desperate, that is an expensive way to raise cash.
Compare it with your margin and your cost of cash
The yearly figure means little on its own. Set it against three things.
Your cost of cash. If you would otherwise use an overdraft or a credit card to cover materials, work out what that costs you over the same number of days. If the discount costs more than the borrowing, borrowing is cheaper.
Your margin. On that £2,000 job, suppose £400 is profit. A £40 discount takes a tenth of it. A 5% discount (£100) takes a quarter. Check the job still pays after the discount.
Whether they would pay quickly anyway. Plenty of homeowners pay by bank transfer the day the job ends. If so, a discount just gives away money you would have had anyway.
When a discount can make sense
A discount is easiest to justify when all of these are true: you have to pay for materials or a subcontractor before the customer pays you, you have no cheaper way to cover that, and the customer is the kind who normally takes the full time or longer. Keep the percentage small and the deadline short, and offer it job by job rather than as a standing rule.
Before you cut your price, look at options that cost you nothing. Asking for a deposit or splitting a big job into stages brings cash in earlier without any discount. Our guide on deposits and stage payments covers how. Pricing the job so it holds up is covered in how to price a job.
If you are VAT-registered
VAT (value added tax) only matters here if you are registered. You must register if your taxable turnover for the last 12 months goes over £90,000, or you expect it to go over £90,000 in the next 30 days. You can also register voluntarily below that. See When to register for VAT. If you are not registered, there is no VAT to think about.
HMRC calls an early-payment discount a prompt payment discount: a reduction in price if the customer pays promptly, after the invoice is issued and before full payment is due. HMRC's example is 5% off if paid within 14 days of the invoice date. Under paragraph 4 of Schedule 6 to the Value Added Tax Act 1994, where the discount terms are met and the discount is taken, VAT is worked out on the discounted price actually paid. The price must not be paid by instalments. HMRC explains this in its VAT valuation manual.
You must decide before you issue the invoice which of two methods you will use:
Method 1: issue a VAT invoice for the full value plus VAT, and show the discount offer and its rate (regulation 14 of the Value Added Tax Regulations 1995, SI 1995/2518).
Method 2: issue an invoice showing the discount terms (including the deadline), the discounted price, the VAT on that discounted price, and the total due if the discount is taken up.
HMRC suggests this wording on the invoice: "A discount of X% of the full price applies if payment is made within Y days of the invoice date. No credit note will be issued. Following payment you must ensure you have only recovered the VAT actually paid." Without the no-credit-note line, a VAT-registered customer has to adjust their own VAT when a credit note arrives. Under Method 2, your VAT invoice and proof you received the discounted amount, such as a bank statement, support the reduced VAT you account for (regulation 38 of the same regulations).
If you use the cash accounting scheme, HMRC's cash accounting manual says VAT is charged on the discounted price even if the customer does not take the offer up. The two manual pages describe the treatment differently, so check with an accountant or HMRC before you offer a discount on VAT jobs.
Late payment: the other side of the coin
If your customers are businesses, the law already gives you something for late payment. Under the Late Payment of Commercial Debts (Interest) Act 1998, statutory interest on a late business-to-business debt is 8% plus the Bank of England base rate, unless your contract sets a different rate. GOV.UK's guidance on charging interest sets this out.
Interest runs from the payment date you agreed. If you agreed none, it runs from the end of 30 days after the work is done or the customer has notice of the amount, whichever is later (section 4). Once interest applies, section 5A adds a fixed sum: £40 for a debt under £1,000, and £70 for £1,000 to under £10,000. Larger debts have a higher sum, which GOV.UK's late payment framework sets out.
GOV.UK frames this as a business-to-business rule, so do not count on it for a homeowner job. Our guide on chasing a late invoice and claiming interest shows the steps.
How to offer a discount without confusion
Run the calculation first and set the lowest discount you would accept.
Put the offer on the quote and the invoice: the percentage, the deadline in days from the invoice date, and the discounted amount in pounds.
Make clear it applies to the whole invoice paid in one go, not part-payments.
Say that after the deadline the full price is due.
If you are VAT-registered, follow HMRC's invoice wording and choose your method before you send it.
When the transfer arrives, check the amount against the discounted figure and keep the bank statement line with the invoice.
Wrap-up
An early-payment discount is a price cut with a high yearly cost, so use it sparingly. Run the numbers, compare them with your margin and the cost of your borrowing, and try deposits and clear payment terms first. If you do offer one, keep the terms plain. With Quidjob you send the invoice from your phone and the customer pays by bank transfer from the invoice link, so you can see quickly whether they met the deadline.