Choose which optional cookies we may use. You can change this any time from “Cookie settings” at the foot of every page. Cookie policy

Getting paid

Deposits and stage payments: a guide for tradespeople

There’s no legal limit on a deposit, but there are rules on cancellation, VAT and, for work for other businesses, stage payments. Here’s how to set it up so you’re paid as the job goes.

Published · 6 min read

A deposit pays for the materials you buy for a job and shows the customer is serious. Stage payments keep money coming in on longer jobs, so you’re never too far out of pocket. This guide covers how much to ask for, what to put on the quote, the cancellation rules for homeowners, VAT, and the extra payment rights you have when you work for another business.

No. UK law doesn’t set the size of a deposit. It’s whatever you and the customer agree.

What homeowners are told matters, though. Citizens Advice tells them not to agree to more than 25% upfront, and says paying in stages is a good idea. Ask for half the price before you start and a careful customer may go elsewhere.

How much deposit to take

These are sensible starting points, not rules:

Kind of job Typical deposit Why
Call-outs, repairs and small jobs No deposit Little or nothing to buy in advance, so invoice when the job’s done.
Jobs with parts or materials ordered for them The cost of those materials, often 10% to 25% Covers what you’d be left with if the customer pulled out.
Bigger projects over several weeks A modest deposit, then stage payments Each payment follows work the customer can see, with the balance on completion.

The deposit calculator works out the deposit, the balance and, if you’re VAT registered, how much of each is VAT.

Put the deposit and stages on the quote

Write the payment plan into the quote, not just the price. For each payment, say:

  • how much it is, in pounds as well as a percentage
  • what triggers it: acceptance, a stage of work finished, or completion
  • what the deposit covers, such as the units or the boiler you’ll order
  • how to pay, with your bank details

Tie each stage to something the customer can see, like “units fitted” or “first fix done”, rather than a date. If the job slips, nobody argues about whether a payment is due. The building quote template has space for a deposit and stages.

Cancellation rights when you agree a job off your premises

Most domestic jobs are agreed in the customer’s home, by phone or online. Those are off-premises or distance contracts, and the Consumer Contracts Regulations give the customer a right to cancel.

  • 14 days to cancel. For services, the period ends 14 days after the day the contract is made. The customer doesn’t need a reason.
  • Don’t start in that time unless asked. Regulation 36 says you mustn’t start work in the cancellation period unless the customer expressly asks you to. For a job agreed in their home, get that request on a durable medium, such as an email, a text or a signed form.
  • If they cancel after you’ve started, they pay an amount in proportion to the work you’ve done, and you refund the rest.
  • Give them the cancellation information. If you don’t, the period runs for a further 12 months. Under regulation 36(6), a customer who then cancels pays nothing for the work already done.
  • Starting without a request costs you too. If you started in the 14 days without their express request and they cancel, they pay nothing for that work either.

Emergency call-outs

There’s an exception for urgent work. Under regulation 28, the cancellation rules don’t apply where the customer specifically asked you to visit for urgent repairs or maintenance. They still apply to any extra work you offer on that visit, and to goods other than the replacement parts needed for the repair. Fix the burst pipe on the spot; quote the new bathroom properly.

VAT on deposits

If you’re VAT registered, a deposit carries VAT. HMRC’s VAT guide treats a payment received in advance as creating a tax point, so the VAT in the deposit belongs on the return for the period you received it. Each stage payment works the same way. If you’re not registered, none of this applies. Ask an accountant if your jobs straddle VAT periods and you’re unsure where something goes.

Work for other businesses: the Construction Act

When you work for a builder, landlord, developer or main contractor, Part II of the Housing Grants, Construction and Regeneration Act 1996 gives you payment rights by law, and a statutory Scheme fills any gaps in the contract. It covers England, Wales and Scotland, and the contract doesn’t need to be in writing.

  • Stage payments. You’re entitled to stage or periodic payments unless the work is specified, or agreed, to last less than 45 days.
  • Payment notices. The contract must provide for a payment notice no later than five days after each payment due date, saying what’s due and how it’s worked out.
  • Pay less notices. The payer must pay the notified sum unless they give a pay less notice in time. Under the Scheme for Construction Contracts, that’s no later than seven days before the final date for payment. The Scheme sets the final date at 17 days after the due date.
  • Pay-when-paid doesn’t work. A term saying you’ll be paid only when the main contractor is paid is ineffective, unless someone up the chain is insolvent.
  • Right to suspend. If you’re not paid the sum due, you can suspend work after giving at least seven days’ notice of your intention to suspend, stating the grounds. The other side pays your reasonable costs.
  • Adjudication. You can refer a dispute to an adjudicator, who must decide within 28 days of the referral unless more time is agreed. The decision is binding unless a court, an arbitrator or an agreement later says otherwise.

None of this covers homeowners. Section 106 excludes contracts with a residential occupier: work mainly on a house or flat that the customer lives in or plans to live in. For those jobs, your payment terms are whatever your quote says.

Retentions

A retention is a percentage of each payment that the contractor holds back and releases later. The Commercial Payments Bill proposes banning retention clauses in construction. It’s still in the House of Lords, with its third reading listed for 20 October 2026, so it isn’t law. For now, read the retention terms before you sign and put the release dates in your diary.

Variations

Extras are where margins disappear. Before you do anything outside the quote, agree it in writing with the price: a text or email saying what the change is, what it costs and whether it moves the finish date. Add it to the next stage payment, or invoice it on its own. A variation agreed only by a nod on site is the one the customer disputes later.

Worked example: a £12,000 kitchen in three stages

You quote a homeowner £12,000 to fit a kitchen over three weeks, agreed at their house.

Stage When it’s due Amount
Deposit (20%) On acceptance, to order the units and worktops £2,400
Stage 2 (50%) Units fitted and first fix finished £6,000
Balance (30%) On completion £3,600
Total £12,000

The deposit sits under Citizens Advice’s 25% and covers the order. Because you agreed the job in their home, give them the cancellation information with the quote. If they want you to start within the 14 days, get that request in writing. If they then want a tiled splashback added, send the price and get a yes before you tile, and add it to the final stage. If you’re VAT registered, the VAT on each payment falls in the period you receive it.

If a stage payment is late, the guide to chasing a late invoice covers what to send and when.

How Quidjob helps

Quidjob quotes show the deposit, the stages and the balance. You send the quote as a link by email, or by WhatsApp or text from your own phone, the customer accepts online and pays the deposit by bank transfer straight to your account, and variations go to the customer for approval with their price. If an invoice goes unpaid, Quidjob chases it politely and stops when it’s paid. You can try Pro free for 14 days, with no card; after that the Free plan keeps 3 quotes a month.

Official sources

Last checked 17 October 2026 against citizensadvice.org.uk, legislation.gov.uk, GOV.UK, bills.parliament.uk. General guidance for UK businesses, not legal, tax or financial advice. For your own situation, ask HMRC, an accountant or a solicitor.

Questions

Anything else? Email hello@quidjob.co.uk.

Is there a legal limit on how much deposit I can take?

No. UK law doesn’t set the size of a deposit, so it’s whatever you and the customer agree. Citizens Advice tells homeowners not to agree to more than 25% upfront and says paying in stages is a good idea, so asking for much more than that can cost you the job.

Can a customer cancel and get their deposit back?

If you agreed the job in the customer’s home, by phone or online, they usually have 14 days to cancel. If you started early at their express request, they pay for the work done so far. If you never gave them the cancellation information, the period can run for 12 months more and they may owe nothing for work already done.

Do I charge VAT on a deposit?

If you’re VAT registered, yes. A payment received in advance creates a tax point, so the VAT included in the deposit goes on the VAT return for the period in which you received it, not the period in which you finish the job.

Do the Construction Act payment rules apply to work for homeowners?

No. Part II of the Construction Act doesn’t apply to a contract with a residential occupier, meaning work mainly on a house or flat that the customer lives in or intends to live in. It does apply to work for builders, landlords, developers and other businesses, so subcontract work is usually covered.

Send the invoice. Get paid by bank.

Quotes, invoices and bank transfers for UK trades. 14 days free, no card needed.

Start free