You finish a job, send the final invoice, and the customer pays everything except a slice. They say it is 'retention' and you will get it later. Later can mean months, and small firms often lose track of it. This post explains what retention is, where you are likely to meet it, and what to do so the money actually reaches you.
What retention means
Retention is a part of the contract price that the customer keeps back after the work is done. The idea is that they hold some money as security while any faults are put right. You are then paid the retained amount when the contract says it is due, usually once the work has been signed off or a set period has passed without problems.
It is a term of the contract, so the details depend on what you agreed. The amount, the trigger for release and the date should all be written down. If they are not, you have little to point to when you ask for the money.
When you are likely to meet it
Retention is more common on larger or longer jobs, and on work where you are a subcontractor for a main contractor. It is much less common on a one-day repair for a homeowner. Research published with a government consultation in 2017 found that around three-quarters of contractors surveyed had experience of retention in the previous three years, and that those contractors had retention held on an average of 65% of their current contracts. That is old data, but it shows how normal it is across the industry.
Expect to see it in:
subcontract agreements from a main contractor
contracts for extensions, new builds or larger refurbishments
commercial or landlord work with a formal contract
any contract that mentions 'practical completion' or a 'defects period'
What the law says
The main law for payment on construction work is the Housing Grants, Construction and Regeneration Act 1996, often called the 'Construction Act'. A government consultation on retention explains that changes made in 2011 mean payment can no longer be made conditional on the performance of obligations under another contract. In plain terms, a customer should not tie your payment to something that happens under a different contract.
The same consultation accepts that some delays and non-payments can be for legitimate reasons. Its examples are while defects are being fixed, or where the contractor has not come back to fix them. So retention is not automatically unfair. If you have faults to put right, expect the money to stay held until you do.
Does the Construction Act cover homeowner work?
Many sole traders work mainly for homeowners. Section 106 of the Construction Act says its payment rules do not apply to a construction contract with a residential occupier: a contract mainly about work on a house or flat that one of the parties lives in, or intends to live in. So if you work for a homeowner living in the property, your rights depend mainly on your own contract and on general contract law. If you are unsure, take legal advice, because your situation may differ.
Before you start: get retention into the contract
The best protection is agreeing the terms before any work begins. Read the contract or purchase order and look for the word 'retention'. If it is there, make sure you can answer these questions:
How much is held back, and is it a percentage of the whole price or of each payment?
What triggers release: practical completion, sign-off, or the end of a defects period?
Is there a fixed date for release, and how long is any defects period?
Who decides the work is complete, and how will they tell you?
How and when do you invoice for the retained amount?
If an answer is missing, ask for it in writing. A short email confirming 'retention of £1,000 to be released within 14 days of sign-off' is far better than a verbal promise. If the customer wants to add retention part-way through a job, treat it like any other change and get it agreed in writing first.
Keep track of what is owed
Held-back money is easy to forget because it is not on your list of overdue invoices. A simple retention log fixes that. For each job, record:
the customer and job address
the contract price and the amount retained
the date the work finished or was signed off
the date retention is due for release
the date you asked for it, and the reply
Put the release date in your phone calendar with a reminder a week earlier. This matters most when the due date is many months after you have moved on to other work.
Worked example: you finish a £20,000 extension and the contract holds back £1,000 until the defects period ends. You are paid £19,000 now. Your log says the remaining £1,000 is due on the release date. If you have not heard anything a week before, you contact the customer first rather than waiting.
Making sure the money is released
Deal with snagging quickly
A customer can legitimately hold money while faults remain. Respond fast to any snagging list, fix the items, and ask for written confirmation that they are done. Photos with dates help if there is a later argument.
Ask at the right time
When the release date arrives, send a clear invoice or request for the retained amount. Quote the contract, the job, the amount and the date it fell due. Keep the tone polite and factual.
Chase if it is not paid
If the date passes, follow up in writing and keep copies. Our guide to chasing a late invoice and claiming interest covers the steps. If the customer disputes part of it, see the post on getting paid when a customer disputes part of the invoice. If the amount is large, get advice before taking further action.
Other ways to protect your cash flow
When you price a job with retention, remember that part of your money will arrive late. Allow for that in your cash flow, and think about whether deposits and stage payments can reduce the amount at risk. Our guide to deposits and stage payments explains how to set them up.
Retention can also affect your tax and VAT records, and how it is treated under the Construction Industry Scheme (CIS) if you work as a subcontractor. Check HMRC's guidance or ask an accountant for your situation. If you use Quidjob, you can keep the quote, invoices and job notes together, so the retention amount and release date are in the same place as the rest of the job.
Wrap-up
Retention is a normal part of larger building work, but it is only as safe as the terms you agreed. Get the amount and release date in writing, log every retained sum, fix snags promptly and chase on the due date. If you work for a homeowner, check how the Construction Act applies to you, and ask an accountant or solicitor if the sums are significant.