Two days ago, on 15 October 2026, the previous version of the Wiring Regulations was withdrawn. BS 7671:2018+A4:2026 is now the only current edition. If you’ve been finishing jobs on the old forms, now is the time to switch. Here’s what’s changed and what it means day to day.
What happened on 15 October
Amendment 4 was published on 15 April 2026, with a six-month overlap. According to NICEIC, the version it replaces, BS 7671:2018+A2:2022+A3:2024 and the 2023 corrigendum, has now been withdrawn, and Amendment 4 became the only version on 15 October. The IET’s Amendment 4 page confirms it’s available.
In practice, the certificates and reports you issue from now on should be on Amendment 4 forms and say so.
New model forms, free from the IET
The IET has published model forms for Amendment 4: the Electrical Installation Certificate, the Minor Electrical Installation Works Certificate, the EICR and a supplementary bonding schedule, plus an all-in-one PDF. They’re free to use in your electrical contracting business. You can’t resell them or use the IET logo, and the permission lapses after 7 years.
One detail to catch on the Minor Works form: the end-to-end resistance readings are now labelled r1-r1, rn-rn and r2-r2.
FI no longer makes an EICR unsatisfactory
This is the change landlords and agents will notice. On the Amendment 4 EICR form, the overall assessment is unsatisfactory only if there’s a C1 (danger present) or a C2 (potentially dangerous). C3 (improvement recommended) and FI (further investigation advised) are advisory and don’t affect the outcome.
Under Amendment 3, an FI made the installation unsatisfactory. NICEIC calls it one of the most impactful changes for EICRs. So a property that failed last year on an FI alone could come back satisfactory now, and an FI still means something needs looking at. Write it up clearly, and price the investigation separately so the landlord can decide.
For rented homes in England, the rented-sector regulations still talk about further investigation. A proposed amendment would bring them into line, but it isn’t law yet. Our EIC vs EICR guide goes through the codes in full.
What else is in Amendment 4
NICEIC’s summary of the headline changes includes:
a new Chapter 57 on stationary secondary batteries
Section 545 on functional earthing, including for ICT
Section 716 on power over ethernet
a revised Section 710 for medical locations
PNB earthing arrangements
RDC protective devices for EV charging
new wording on AFDDs for high-rise residential buildings
Social landlords: older tenancies due before 1 November
Social landlords in England now have the same electrical safety duties as private landlords, under SI 2025/1043. For social tenancies granted before 1 December 2025, the gov.uk guidance says the first inspection must be done before 1 November 2026. If you work for housing associations, expect a rush of late EICR requests over the next fortnight. Our landlord gas safety and EICR guide covers the full rules.
If you’re quoting that work, Quidjob issues EICRs, EICs and Minor Works certificates and reminds you when each inspection is due again. The free plan includes 3 quotes a month: start free.