The Construction Industry Scheme (CIS) is the system where a contractor takes a percentage off what they pay a subcontractor and sends it to HMRC. If you bill materials separately, you will want to know whether that part is hit too. The answer depends on what the invoice actually is, and on whether you can prove what the materials cost you.
Two different situations that get mixed up
People say materials-only invoice to mean two quite different things. The first is a straight sale of materials with no fitting. The second is a line for materials on an invoice for work you are doing under a CIS contract.
Making materials and delivering them to site are excluded from construction operations. HMRC cites section 74(3)(c) and (d) of the Finance Act 2004 for this in its guidance on manufacture and delivery. Its examples include traditional building materials, ready-mixed concrete and painting or decorating materials. Installing manufactured items under a supply and fix arrangement is inside CIS.
Supply and delivery only: this is not CIS work, so the CIS deduction doesn't arise.
Supply and fix: the fitting is CIS work, and the materials are handled through the deduction rules below.
Materials line on a CIS invoice: the contractor deducts from the payment less the direct cost of the materials.
What the law says about materials
Under section 61(1) of the Finance Act 2004, the contractor deducts the relevant percentage from so much of the payment as is not shown to represent the direct cost to the subcontractor of materials used or to be used in the work. The key words are direct cost and shown.
HMRC's manual on materials reads direct cost as what you can demonstrate you paid for the materials yourself. A few points follow from that:
The materials must relate to the contract the payment is made under.
Only the subcontractor who buys the materials directly can take them off before the deduction (CIS 340, paragraph 3.13).
If the contractor supplies the materials and you don't pay for them from your own business, you can't deduct their cost.
Because the law speaks of direct cost, any mark-up you add is part of the payment the deduction is taken from.
Contractors also don't take a deduction from some other amounts on your invoice, according to GOV.UK's page on getting paid as a CIS subcontractor. These are VAT, consumable stores, plant hired for the job, manufacturing or prefabricating materials, and materials you have paid for directly.
A worked example
These figures are made up to show the method. Say you are registered for CIS and the contractor can verify you, so the standard rate of 20% applies. You are not charging VAT. You fit a bathroom for a contractor and invoice £800 for labour and £450 for materials. Your receipts show you paid £450 for those materials.
Total invoice: £800 + £450 = £1,250.
Take off the direct cost of materials: £1,250 − £450 = £800.
Deduction at 20% of £800: £160.
You receive £1,250 − £160 = £1,090.
Now say you added a £50 mark-up and charged £500 for materials that cost you £450. The deduction is taken from £850, so it is £170. If you were unverified and on the higher rate of 30%, the deduction on £800 would be £240.
When the materials figure is missing or looks too high
If the contractor can't get satisfactory information about the materials, HMRC's manual says they may make a reasonable estimate of the cost and deduct from the rest. GOV.UK says the same: with no evidence, the contractor estimates the cost.
The same goes if the materials charge looks overstated. The manual gives the example of a supply and fix job where the subcontractor says the whole charge is for equipment and the installation is free. A mark-up doesn't stop the contractor estimating the cost if you won't disclose it. The contractor must check and keep records so the materials part isn't overstated. If it looks excessive, HMRC may recover any under-deduction from the contractor, which is why they may push back on your figures.
Plant, fuel and other costs
Plant hired from a third party can be treated as materials, along with consumables such as fuel. If you own the plant, no notional hire charge is allowed, though fuel and other consumables can still count. Travel and subsistence paid to you or on your behalf stay in the amount the deduction is taken from.
Evidence worth keeping
Official guidance mentions receipts and records of direct cost. It doesn't give a fixed checklist, so the habits below are sensible suggestions, not an HMRC requirement.
Receipts or invoices in your name for the materials, kept with the job they were for.
Merchant statements that match your receipts.
Separate lines for labour and materials on your invoice, showing materials at cost and any mark-up as its own figure.
A note of which contract or site each purchase belongs to.
The payment and deduction statements the contractor gives you.
The contractor must give you a statement within 14 days of the end of each tax month. The tax month runs from the 6th to the 5th, so that is by the 19th. It must show the gross payment, the cost of any materials that reduced the amount the deduction was applied to, and the deduction. Check the materials figure against your own records. The contractor's monthly return is also due by the 19th: for 6 May to 5 June, that is 19 June.
Contractors must keep records of payments, materials and deductions for at least three years after the end of the tax year they relate to (CISR12200). It makes sense to keep yours at least as long.
Keeping the split tidy
If you quote and invoice with Quidjob, you can set out labour and materials as separate lines from your phone and keep the job's records together. Customers pay by bank transfer from the invoice link. The app doesn't change the CIS rules, it just makes the evidence easier to find when a contractor asks.
Wrap-up
A pure supply of materials isn't CIS work. Materials on an invoice for CIS work come off the deduction only up to what you can show they cost you, for that contract. Keep receipts, itemise your invoices and check each statement. This is general information, not tax advice. If your situation is unusual, ask an accountant or check the official pages. For the wider picture, see CIS explained for subcontractors.